XXL distribution centre, Hulst

De Hoop Betonmortel delivered the last concrete in early February 2024 for the impressive XXL distribution center located at the Hogeweg business park in Hulst. With a total size of approximately 118,000 square meters and over 1,000 parking spaces, this project marks a milestone for Zeeuws-Vlaanderen.

De Hoop Betonmortel played a significant role in realizing this project. Over the past few months, up to 450 cubic meters of concrete were delivered daily. This amounts to about 40 to 45 concrete mixers delivering concrete to the construction site each day.

Emphasis on sustainability and biodiversity was a key feature of the modern distribution center located on a plot of over 20 hectares. Throughout the project, special attention was given to enhancing the natural environment by using native plant species.

In total, more than 33,500 m³ of ready-mixed concrete was supplied for this memorable project. De Hoop Betonmortel is proud to have contributed to the successful realization of this distribution center and looks forward to the project's further progress.

The first phase of DC XXL was completed in the second quarter of 2024, with the completion of the second phase expected by mid-2024. De Hoop Betonmortel remains committed to providing high-quality concrete supplies and is eager to support future construction projects in the region.